Who This Checklist Is For
-
Step 1: Define the Inspection Task in Numbers, Not Words
-
Step 2: Lock Down the Camera Specification Tier First
-
Step 3: Separate the Integrator from the Hardware Vendor
-
Step 4: Demand a Sample Test on Your Actual Parts
-
Step 5: Write Delivery, Acceptance, and Downtime Clauses Into the PO
-
Step 6: Plan the Integration, Not Just the Vision System
-
Step 7: Get Training and Support Terms in Writing
-
Things That Often Go Wrong
Who This Checklist Is For
If you're sourcing a machine vision system — whether it's a 2D setup for defect detection on a high-speed line, or a 3d machine vision system for bin picking and dimensional measurement — this checklist is for you. It assumes you have a live deadline, a fixed inspection requirement, and no appetite for a six-week discovery phase.
I'm writing this from the procurement and integration side. I've handled 40+ vision-related orders over six years — some were planned, some were emergencies where a line was already down. The steps below are the ones I actually run, in order, before I sign anything.
There are 7 steps. Steps 1 and 4 are the ones most buyers skip, and they are also the two that cause the most rework.
Step 1: Define the Inspection Task in Numbers, Not Words
Before you call a single vendor, write down five numbers:
- Part size and field of view (mm)
- Required resolution or smallest defect (µm)
- Line speed or cycle time (parts per minute)
- Reject rate and target false-positive rate
- Operating environment (temperature, dust, vibration, ambient light)
I can't tell you how many RFQs I've seen that say "detect scratches" without a size threshold. A 50 µm scratch and a 500 µm scratch are two completely different optical setups — different lenses, different lighting, sometimes a different camera class altogether.
I'm not an optics engineer, so I can't speak to lens distortion modeling or MTF curves. What I can tell you from a sourcing perspective is this: vendors quote what you ask for, not what you meant. Vague inputs produce vague quotes, and the gap always shows up after the PO is cut.
Honestly, the single biggest source of rework I've seen in machine vision system sourcing is a one-page RFQ that should have been five.
Step 2: Lock Down the Camera Specification Tier First
For most machine vision system applications — presence/absence, positioning, OCR, surface defect detection — the camera tier drives 40–60% of total system cost. Sorting it first saves you from redesigning the whole system around the wrong sensor.
Three questions that narrow it fast:
- Is a standard 2D area or line scan sufficient, or do you genuinely need depth? (Most "we might need 3D" cases don't.)
- Is the part stationary at capture, or moving?
- Do you need to inspect color, or is monochrome enough?
If the answer to #1 is genuinely yes — say, for volume measurement, robot guidance, or inspection of complex freeform surfaces — then a 3d machine vision system is justified. Otherwise you're paying for depth you'll never use.
Step 3: Separate the Integrator from the Hardware Vendor
This is a distinction most first-time buyers get wrong. A camera brand (Cognex, Keyence, Basler, and others) sells hardware and licensed software. A machine vision system integrator sells a working solution — camera, lens, lighting, mounting, software configuration, PLC handshake, and on-site commissioning.
You generally need both, but you negotiate with them differently. Hardware vendors compete on specs and price. Integrators compete on project risk. For an emergency deployment, integrator quality matters more than camera brand.
In my experience, the second- or third-largest integrator in a region often delivers faster than the biggest one, simply because you get senior engineers on the project instead of a rotating bench.
Step 4: Demand a Sample Test on Your Actual Parts
Most buyers skip this. A specification sheet cannot tell you whether your specific surface finish will produce specular reflections that break the algorithm, or whether the coating on your parts absorbs the wavelength your lighting emits.
Send 20–30 real parts — including known-good and known-defective — with clearly labeled pass/fail expectations. Ask for a written test report that states the achieved detection rate and false-positive rate on that sample.
The numbers said the vendor's benchmark case matched our requirement on paper. My gut said the sample test would reveal something. It did — their default lighting produced glare on our brushed-aluminum surface, and the fix added two weeks to the schedule. We found it in week one, not week six.
Step 5: Write Delivery, Acceptance, and Downtime Clauses Into the PO
For any machine vision system for automatic inspection, define acceptance in measurable terms before the PO is signed:
- Detection rate on the agreed sample set (e.g., ≥ 99.5%)
- False-positive rate (e.g., ≤ 1%)
- Cycle time at full line speed
- Acceptance window (e.g., 5 consecutive production days without unplanned vision-related stops)
- Remediation timeline if the system fails acceptance
None of this is adversarial. Integrators who push back on measurable acceptance criteria are telling you something useful about their confidence level.
Step 6: Plan the Integration, Not Just the Vision System
A vision system that detects defects but can't tell the PLC to eject the part is a demo, not a deployment. Before the vendor ships anything, confirm:
- The communication protocol (EtherNet/IP, PROFINET, Modbus TCP, digital I/O)
- Where the reject signal goes and what downstream action it triggers
- Who owns the HMI (operator screen) and who trains operators
- Whether the mount has clearance from existing tooling and cabling
I've lost count of vision projects that passed a bench test and then stalled on-site because nobody checked the cable route behind the conveyor.
Step 7: Get Training and Support Terms in Writing
Two questions determine your total cost of ownership far more than the sticker price:
- How many hours of on-site training are included, and who conducts it?
- What is the guaranteed response time on a vision-related line stop?
For sourcing purposes, ask for the support SLA in writing. "We respond quickly" is not an SLA. "Remote response within 2 hours; on-site within 24 hours" is.
Things That Often Go Wrong
A few recurring failure patterns worth flagging:
- Chasing the lowest quote. After three failed machines from discount integrators, we now treat any quote more than 25% below the median as a signal to walk, not a signal to negotiate.
- Over-specifying resolution. A 45 MP camera inspected at 60 fps produces a data stream most on-site edge computers can't process in real time. Higher resolution is not automatically better.
- Skipping the environmental review. Ambient light from a nearby window changes across the day, and any system not tested under production lighting conditions will drift in detection consistency by mid-afternoon.
- Treating 3D as a drop-in upgrade. 3D machine vision system integration typically requires different mounting, calibration, and cycle-time budgeting than 2D — plan for a longer commissioning window.
The 5 minutes you spend checking whether the sample test was run under production lighting will save you the 5 days it takes to diagnose inconsistent rejects after go-live. This is the pattern I keep running into, year after year. The honest version is that I'm not sure why the temptation to skip verification is so persistent — maybe because under deadline, the checklist feels like the slow option. In practice, it's the only fast option that survives contact with a live production line.
Use this list as-is for standard 2D inspection projects. For complex 3D or multi-station systems, treat it as a starting skeleton and add a dedicated FAT (factory acceptance test) step before shipment. Pricing and lead times vary widely by region and configuration — request current quotes from at least three integrators before finalizing any budget line.