Who this checklist is for

If you're sourcing a machine vision system and there's already a production date on the calendar, this is the list I hand to our internal team. Nine steps, roughly in the order I run them.

Some context on where I'm coming from: I work in quality and brand compliance for a mid-size contract manufacturer. I review something like 200 supplier deliverables a year — maybe 180, I'd have to pull the log — and in 2025 I rejected around a quarter of first submissions. Almost none of those rejections were about the camera. They were spec mismatches that surfaced at the acceptance test.

So this list is deliberately front-loaded with boring specification work. What kills machine vision projects is ambiguity nobody forced into the open early enough. The technology part is usually the easy part.

Step 1: Define the defect, not the technology

Before anyone says "3D" or "line scan" or "deep learning," write down what you're actually rejecting parts for. Scratch depth? Missing solder? A label in the wrong position? A connector off by 0.2 mm?

I ask for a defect dictionary: defect type, occurrence rate per thousand parts, and whether it's cosmetic or functional. If your QA team can't agree on which of two borderline parts is a reject, no system will agree either. Fix that first — that's most of the work in machine vision system applications that fail.

This is also where you decide whether you need a 2D or a 3D machine vision system. Most people jump to 3D because it sounds more capable. In my experience, maybe 6 out of 10 applications quoted as 3D don't need depth data at all — they need better lighting.

Step 2: Write the acceptance test before the RFQ

This is the step most teams skip, and it's the one that costs the most money.

Before I send a request for quotation, I write the protocol that will decide whether we accept the system: which parts, which defects, how many samples, what pass rate counts as passing, and who signs off. Why before? Because once quotes are on the table, everyone starts negotiating toward the loosest interpretation of the spec. If the acceptance criteria exist first, they're a requirement, not a bargaining chip.

We learned that the hard way. In 2023 we accepted a system on a verbal "it catches the obvious ones," then discovered at commissioning that our definition of "obvious" and theirs differed by roughly a factor of three on defect size. Rebuilding the optics and lighting added about $22,000 — no, closer to $24,000 once I count the downtime. The protocol comes first now.

Step 3: Split hardware and integration in the quote

Ask for three numbers, separately:

  • Hardware — camera, lens, lighting, controller, enclosure
  • Integration and programming — recipe development, PLC/robot communication, HMI, MES handoff
  • Service and support — warranty terms, response time, spare parts

A bundled number hides where your risk sits. On one project hardware was 35% of the total and integration was 50%. On another it was the reverse — same nominal "machine vision system" scope.

Splitting it also lets you compare machine vision system integrators on the part that actually differentiates them. Anyone can resell a camera. Not everyone can build a recipe that survives a lighting shift on second shift.

Step 4: Send your own parts — good, marginal, and bad

Do not accept a demo on the integrator's sample set. Send three groups: known-good parts, known-marginal parts (the ones your inspectors argue about), and known-bad parts.

Then ask two questions:

  1. What's the escape rate on the bad parts?
  2. What's the false-reject rate on the marginal parts?

The second number is the one that kills production. A system that catches everything but rejects 3% of good parts gets switched off by the line supervisor within a week. I'd rather have 98% detection and 0.2% false rejects than 99.9% detection and 3% false rejects. That said, it's a judgment call — it depends on whether your defect is cosmetic or safety-critical.

Step 5: Make 3D claims cite a standard

Any time a supplier quotes measurement accuracy on a 3D machine vision system, I ask which standard the number comes from. Two come up most often:

  • VDI/VDE 2634 Part 3 — acceptance testing for optical 3D measuring systems based on area scanning, including fringe projection and stereo. It defines how form and probing error are tested across a measurement volume.
  • EMVA 1288 — standardized characterization of image sensors and cameras: quantum efficiency, temporal dark noise, saturation capacity, dynamic range.

Neither standard tells you the system will work on your part. But they tell you whether the number you were handed is a measured characteristic or a marketing round-up. "±0.05 mm" with no method attached isn't a specification. It's a hope.

Step 6: Fix lighting and optics before you upgrade the camera

This is the counterintuitive one, and it's why so many projects underperform.

When I compared two of our own lines side by side — same camera model, one with a properly baffled dome light and one with an off-the-shelf ring light — the difference in defect contrast was larger than anything we got from doubling sensor resolution. The dome light setup ran about $1,400 more per station. Across four stations that's roughly $5,600, though I might be misremembering the exact figure. It cut our false-reject rate enough that we retired a manual re-inspection station, which was a full-time headcount.

Priority order when budget is tight: part fixturing, then lighting, then lens, then camera, then software. Most people work it backwards.

Step 7: Ask who owns the recipe after handover

Machine vision fails slowly. A recipe tuned in June drifts by November — new part supplier, new lubricant, slightly different ambient light. Someone has to retune it.

Get this in writing:

  • Who can edit the recipe — your maintenance tech, or only the integrator?
  • Is the development environment licensed to you, or is it a subscription tied to their support contract?
  • What does a retune cost, and what's the guaranteed response time?

I've watched a $60,000 system become effectively unmaintainable because the recipe sat behind a vendor tool that cost $8,000 a year to keep active. That line was not in the quote.

Step 8: Set FAT and SAT criteria with numbers, not adjectives

Factory acceptance test and site acceptance test. Both need to be pass/fail, not "satisfactory performance."

A workable FAT, from a project I ran last year:

  • 500 parts per defect category, pre-labeled by two inspectors independently
  • Detection rate target agreed in writing
  • False-reject ceiling agreed in writing
  • Cycle time measured over 30 consecutive minutes, not a single best-case run
  • Data output verified against our MES schema before shipping

SAT then repeats a smaller subset on the actual line, with actual operators, at actual line speed. I've watched three systems pass FAT and fail SAT in the past two years. Each time it traced back to fixturing or ambient light that the integrator's lab never reproduced.

Step 9: Price the schedule separately

I have mixed feelings about rush premiums. Part of me thinks charging 15% extra to prioritize a job that's already in the queue is gouging. Another part has watched what genuinely expedited work costs in overtime, second-shift labor, and air freight — and suspects the premium is roughly fair.

Here's the thing, though: what you're buying with a rush fee isn't speed. It's certainty. A locked date, in writing, with a credit or penalty if it slips.

In March 2024 we paid about $3,800 extra to compress an integration schedule by three weeks. The alternative was missing a customer launch window worth roughly $180,000 in first-year volume. That's not a hard calculation.

What I won't do anymore is pay a premium for a vague promise. After getting burned twice by "probably on time" commitments, we now budget for guaranteed delivery or we don't pay extra at all. If a supplier can't put a date and a consequence in the contract, that premium isn't buying certainty — it's buying optimism, and I can get optimism for free.

Common mistakes

Specifying resolution instead of capability. "5 megapixel" tells me nothing about whether you can see a 0.1 mm scratch on brushed aluminum.

Letting procurement own the technical comparison. They're good at commercial terms. They can't tell whether two integrators are quoting equivalent scope.

Skipping the marginal-part test. Everyone tests good parts and bad parts. False rejects live in the marginal ones.

Assuming "standard" means the same thing to both sides. I said "standard field of view." They heard "whatever fits the standard lens." We discovered the mismatch when the camera bracket arrived and couldn't clear the safety guard. A week, gone.

No spare parts list at handover. Ask for it: one camera, one light, one lens, one controller per line, minimum. Industrial camera lead times ran 10–14 weeks in 2024 — I want to say that's improved since, but don't quote me on the current number.

Not documenting the recipe version at sign-off. If you can't prove which recipe was running when the line was validated, you can't prove anything later.

One last note on sequencing

Steps 1 through 3 take maybe two days of internal work. They also determine whether the other six go smoothly. Machine vision system sourcing is roughly 80% specification discipline and 20% purchase order, and the specification part is the one nobody puts in the project plan.

If you're working with a sourcing partner, hand them this list. Not because they can't write their own, but because a shared checklist means you spend your meetings arguing about parts and light instead of arguing about what "acceptance" was supposed to mean.